Crews working for general contractor D.L. Meacham are making good progress on Camden Park. They’ve installed all the underground utilities, graded and installed drainage pipe for the parking lot and poured the concrete for the building that will house Sunday Press, Camden Park’s onsite restaurant. Later this fall, they’ll pour the concrete for the porch building and begin working on the foundation and retaining wall for the pedestrian bridge.
While the hot, dry weather has been tough on the construction crews and Westchase District’s extensive landscaping, it has helped the park’s construction timeline. “It’s too soon to project a completion or opening day for Camden Park, but our schedule has been helped by the lack of rain this summer,” said Irma Sanchez, vice president of projects for Westchase District.